Oodenawi Public School
        Completion Amount: $12,000,000.00
        Owners: The Halton District School Board
        Architects: Snyder Architects Inc.
        
St. Angela Merici Catholic School
        Completion Amount: $8,800,000.00
        Owners: Simcoe Muskoka Catholic District School Board
        Architects: Snyder Architects Inc.
        
Cobourg Collegiate Institute
        Completion Amount: $10,900,000.00
        Owners: Kawartha Pine Ridge District School Board
        Architects: Moffet & Duncan Architects Inc.
        
Da Vinci Public School
        Completion Amount: $9 900 000
Owners: Durham District School Board
Architects: Moffet & Duncan Architects
Springridge Public School
1915 Queensbury Drive, Oshawa L1K 0S1
        Completion Amount:  $9 550 000
        Owners: Durham District School Board 
        Architects: Moffet & Duncan Architects   
        Highlights: Repeat design project were  Everstrong was able to minimize design change requests and keep project well under budget and improve schedule
Anne McCarther Public School
        Completion Amount:  $9 900 000 
        Owners: Halton District School Board 
        Architects: Hossack & Associates Architects  
        Highlights: Another project with time table  reduced by 3 months. Completion of this  project occurred in February with 8 months start to finish. Extensive site preparation also occurred in wet months of spring which was managed through additional Everstrong owned equipment
St Noel French Separate School
        Completion Amount:  $7 000 000 
        Owners: Conseil Scolaire de District Catholique Centre-Sud 
        Architects: Mills & Associates Architects  
        Highlights: Extensive poor soils experienced during the  onset of the project  as well as a  formidable winter were overcome by Everstrong . Everstrong  completed extensive finishing including 50000 sq ft of drywall features
Clara Hughes PS
        Completion Amount: $10 000 000 
        Owners: Durham District School Board 
        Architects: Moffet & Duncan Architects  
        Highlights: Repeat design project where Everstrong was able to minimize design change requests and keep project well under budget and improve schedule.
St Benedict Catholic School
        Completion Amount: $11 500 000 
        Owners: Halton Catholic School Board 
        Architects: Snyder Architects  
        Highlights: Everstrong completed project with mid winter start date and September open. 7 month schedule. 
Irma Coulsen Public School
        Completion Amount: $10 500 000 
        Owners: Halton District School Board 
        Architects: Allen & Sheriff Architects   
        Highlights: With a vastly shortened completion schedule and adverse weather Everstrong was able to complete the project from start to occupancy in 8 months.